Overview level:
For the reader seeking a broad overview of the study area, main issues and findings.
|
Chapter 1 - Summary of Project Findings
Appendix 5 - Maps of the study area
Chapter 6 - Conclusions and Recommendations
|
Assessment level:
For the reader seeking an understanding of the study and assessment process, as well as the integration of all the environmental issues.
|
Chapter 1 - as above
Appendix 5 - as above
Chapter 2 - Environmental Impact Assessment, giving information on route selection, description of the terrain and a listing of the environmental issues.
Appendix 1 - Impact Tables, giving concise summaries on each environmental issue.
Chapter 6 - Conclusions and Recommendations.
|
Detailed Assessment:
Certain readers will have specific interests and may require further detail in these areas. Therefore in addition to the `Assessment level' chapters/appendices, the reader may choose to look into any of the following:
|
Chapter 3 - Overview of the Cape Strengthening Programme, giving the background to the Transmission line proposals, details of the type of line, strategic planning issues, etc.
Chapter 4 - Approach and Methodology, giving assumptions and limitations to the study, the focus of the specialist investigations, impact assessment criteria, etc.
Chapter 5 - Public Involvement Process. This chapter gives details of the consultation programme, identification of stakeholders, advertising of the study, meetings, and a list of registered stakeholders.
Chapters 7 to 12 - Specialist study reports.
Chapter 7 - Bird studies
Chapter 8 - Ecology
Chapter 9 - Heritage
Chapter 10 - Social Impact Assessment
Chapter 11 - Soils
Chapter 12 - Visual Impact Assessment
|
Activity / Event
(see Chapter 1 of the EIR - Section 4).
|
Specific involvement of I&AP's from the ETLAC area (see Chapter 5)
|
|
1
|
The EIA study was initiated in September 1999
|
Background Information Document (BID) prepared and distributed via municipal offices, Co-ops, regional and provincial govt. departments.
|
2
|
As part of the early stages of the Scoping Study a `Strategic Workshop' was held with key stakeholders on 28th January 2000, at Koeberg Power Station.
|
Wolseley Municipality
Ceres Municipality
SAFCOL
|
3
|
A round of Public Open Days were held along the route in the second half of February 2000.
|
Belmont Hotel, Ceres, 26th Feb.
Wolseley Community Hall, 28th Feb.
Tulbagh Town Hall, 1st March
Attendance of the Tulbagh Farmers Assoc. meeting 26th Feb
Meeting with Mr Patrys Theron (Farmers Assoc Chairperson) 28th Feb.
|
4
|
In March 2000 the study was put on hold for strategic planning reasons.
|
|
5
|
A bridging document was sent to all registered I&APs in November 2000.
|
Interim information BID distributed as per first BID, but also posted to all registered I&APs.
|
6
|
The study continued in June 2001. Letters sent to all registered I&APs.
|
Information document distributed as above, giving notice of date and location of availability of Draft Scoping Report (DSR).
|
7
|
Distribution of the Draft Scoping Report (DSR) in July 2001.
|
Advertisements:
National - Sunday Times, Rapport, City Press, Engineering News.
Regional - Cape Argus, Cape Times, the Standard.
Local - Swartland Monitor, Witsenberg Herald
DSR locations
Ceres - Witsenburg Mun. Offices, Library, PLK
Tulbagh - Mun. Offices, Library, WPK
Wolseley - Mun. Offices, Library, Romansrivier Co-op.
|
8
|
Discussions with Farmers Associations along the route - July and August 2001.
|
Ceres Library Hall - 1st August 2001
Ceres District Agric. Union
Koue Bokkeveld Agric. Union
Warm Bokkeveld Agric. Union
Wolseley Agric. Union
Tulbagh - 2nd August 2001
Tulbagh Farmers Assoc.
Tulbagh Agric. Union
|
9
|
Environmental Forum Workshops 13th to 17th August 2001. Date of written notification 16 July 2001
|
Ceres - Belmont Hotel, 16 August 2001
Presentation and discussion of DSR, including route selection process. See list of invited delegates in Annexure 1.
|
10
|
Submission of Final Scoping Report to the authorities on 30th September 2001.
|
|
11
|
Specialist studies - September 2001 to February 2002.
|
|
12
|
Distribution of Draft EIR on 20th March 2002.
|
Registered I&APs notified by letter dated 20th March 2002.
|
13
|
Closure of public comment period on 19th April 2002.
|
|
14
|
Submission of Final EIR (Addendum Report) to the Authorities on 30th April 2002.
|
|
15
|
Issue of Letter of Approval by DEAT
|
Registered I&APs notified by letter dated 2nd April 2002.
|
The strategic issues surrounding the need for the new line are discussed in detail in the EIR. Assuming those arguments are accepted here, it must then be accepted that an additional line from the Mpumalanga power generation area is required to fulfil both current electricity supply reliability and future growth requirements in the Western Cape.
|
See Chapter 3,
Section 2
|
Following the existing 400kV Transmission lines initially appeared to be the best option, though the mountain region near Ceres was a concern. Routes to the north (via Clanwilliam) and south (via Worcester) were considered, but these were either likely to be much longer and/or more technically complex. As such the associated environmental impacts would also prove to be greater than for the route following the existing lines.
|
See Chapter 1,
Section 5.3.3
Chapter 2,
Section 3.1,
Map 1b
|
However, the Ceres mountain region (including the Witsenberge, Skurweberge, Watervalsberge and Elandskloofberge) still remained a concern from an environmental perspective, and other routes were considered.
|
See Chapter 2,
Section 3.2,
Map 1a
|
By the end of the Scoping Study, after consultation at both a regional and local level, the route alternatives were narrowed to three main options and one localised deviation (refer to the copy of Map 2a of the EIR, attached).
The `Southern Route' followed the existing 400kV lines past Ceres and Wolseley.
The `Central Route' (eventually became the `Preferred Route') follows the base of the Waboomberge, passes through the Agter Witzenberg and Tulbagh valleys and crosses the Obiekwaberge near Gouda. This is the route that passes just to the south of the town of Tulbagh. The basis for this route was to cross low points in the mountain ranges, this being seen to have both technical and environmental benefits.
(Note there was also the `Central Alternative' that offered a localised deviation through the Agter Witsenberg valley, but the route through the Tulbagh valley is the same as the `Central Route'. For the purposes of this letter, the `Central Alternative' is not considered in any detail here.)
The `Northern Route' leaves the existing 400kV lines just before entering the mountain region near Karoopoort. It deviates through the valley behind the Waboomberge before joining the `Central Route' just before the Agter Witzenberg valley. The basis for this route was to avoid the Ceres valley entirely. Similar effort was given for the Tulbagh valley, but the terrain to the north proved to be too high, rugged and inaccessible. Hence the `Northern Route' joins the `Central Route' near the Gydo Pass.
|
See Chapter 2,
Section 3.3,
Map 2a
Section 5.2
|
It is also important to note that the impact of a linear development such as a Transmission line is seldom of direct benefit to locations along the route; ie the environmental impact at any point is usually negative. Instead such developments are for the regional and national good. Choosing the best alternative is then a case of looking for the option with the least environmental impact. This can be somewhat subjective and therefore debatable, especially with stakeholders. To minimise the effects of this the following are relevant:
The environmental consultant has no vested interest in any of the locations along any of the routes.
The consultant also has nothing to gain from the development (or not) of the line.
The overall assessment in the EIR is the integrated assessment of a team of specialists, and not just from one person.
The study team was informed by I&APs who participated in the process (see Annexure 1).
The details of the assessments are provided such that the authorities may change the preferred route should they consider this to be appropriate.
|
See Chapter 4
|
The public consultation process is fully described in the EIR. There was particular activity in the Ceres-Tulbagh-Wolseley area for the duration of the study. Key members of the community were active in participating in the various meetings and were sent the various document packages. The involvement of the stakeholders listed in Annexure 1 was instrumental in the identification and assessment of routes through the Ceres valley, the Agter Witzenberg, and the Tulbagh valley.
|
See Chapter 5
|
It is important to understand that the location of a line is determined not only by conditions at a point but by the conditions some way ahead and behind as well. This was considered in both selecting and assessing the route alternatives.
|
![]() |
There are two main routes through the Tulbagh valley: the Southern Route and the Central Route (the latter becoming the Preferred Route). A summary of the key issues relating to the two routes are given below. This is a very brief summary. It is necessary for the ETLAC to read the relevant sections of the EIR to see the greater detail of the assessment:
|
See Chapter 2, Table 5
Section 5.2.3
|
In terms of Avifauna (birds) the route of preference would be to follow the existing 400kV lines past Ceres and Wolseley (the Southern Route). Under these circumstances the risk of increased bird mortality due to collision would be low. However, with the recommended mitigation measures (bird flappers on the new line at key locations) the impact of the Central Route is still anticipated to be low.
|
Chapter 2,
Section 5.2.3,
App 1 - Impact Tables p30-31,
Chapter 7
|
In terms of indigenous flora, the Central Route is considered to be the best option as the natural vegetation is more disturbed, mainly due to agriculture and urban development. Following the existing 400kV lines the Southern Route would impact on important Central Mountain Renosterveld in the Elandskloof Nature Reserve and on the lower slopes of the Witsenberge in the Wolseley area.
|
Chapter 2,
Section 5.2.3,
App 1 - Impact Tables p32-35,
Chapter 8
|
Erosion is also a particular concern affecting the natural environment, and this is seen to be a greater problem on the Southern Route where the mountain crossings are much higher, less accessible and more sensitive to erosion. While the potential for erosion is also significant along the Central Route, there is better access and greater potential for monitoring and rehabilitation.
|
Chapter 2,
Section 5.2.3,
App 1 - Impact Tables -p29,
Chapter 11
|
For indigenous fauna, the main concern is the Geometric Tortoise that exists in pockets of Renosterveld throughout the area, but is more prevalent on the Southern Route. Hence again the Central Route is preferred in this regard, though the farm Skilpadrug, just south of Tulbagh, is known to be a location of the tortoise. Careful management during construction will be required if the lines passes through this site, or the line should be moved approximately 500m northwards.
|
Chapter 2,
Section 5.2.3,
App 1 - Impact Tables -p28,
Chapter 8
|
From a Cultural heritage perspective the Southern Route offers the least impact, as the new line would run next to the existing 400kV lines. There are a number of historically significant sites along the Central Route, mainly in the Agter Witsenberg; a possible VOC cannon site, the possible remains of a British fort, and the old wagon trail to Wuppertal. The `sense of place' of the historic slave settlement of Steinthal near Tulbagh will be negatively affected, as will possible war grave sites in the Ceres mountains. The old wagon trail between Tulbagh and Gouda is also close to the Central Route. With the exception of the `sense of place' at Steinthal, all of these sites can be avoided by careful placement of the towers, and careful management of the construction process will be required. However, the Southern Route would be the preferred route from a heritage perspective.
|
Chapter 2,
Section 5.2.3,
App 1 - Impact Tables p37-39,
Chapter 9
|
The social impact assessment (SIA) identified the resettlement, disruption and safety of communities along both the Southern and Central Routes to be potentially significant. Communities in Prince Alfred Hamlet, Chris Hani Settlement (both Central Route) and Ceres may be affected, though the proximity of the Bella Vista community to the Southern Route is of particular concern as the relocation of properties may be required. On either route some resettlement may be required, but the impacts on the social fabric of communities along the Southern Route were rated greater.
|
Chapter 2,
Section 5.2.3,
App 1 - Impact Tables p3,8,11-23,
Chapter 10
|
The height of the 765kV Transmission line and the size of the towers will make the development highly visible whichever option is adopted, though following the existing 400kV lines (Southern Route) is considered to offer the least visual impact.
|
Chapter 2,
Section 5.2.3,
App 1 - Impact Tables p4-6,
Chapter 12
|
Initial route identification for alternatives to following the existing lines placed particular emphasis on the visual impact. With particular reference to the Central Route the following refer:
Avoid crossing high points on ridges to avoid the silhouette of the pylons.
In lower areas set the line against complex backdrops (towers more difficult to see) - this is achieved in particular along the Waboomberg, but also on the Skurweberge and Witsenberge.
Follow `low' points in the valleys such that the visual impact from the main viewing points (eg main roads) is minimised. This is seen to be achieved in part in the Tulbagh valley and in the Agter Witsenberg.
Cross over main roads (critical viewpoints) at right angle as this exposes the line to viewers for the shortest period.
|
Chapter 2,
Section 5.2.3,
App 1 - Impact Tables p4-6,
Chapter 12
|
The route through the Tulbagh valley (the Central Route) was identified after input was received from the local community, and in particular from Steinthal School and the Farmers Union. By siting the line to the south of the town, there would be much less impact on landuse (agricultural activities) and the visual impact would be less. The main viewpoint would be the R46 and the line would be visible to road users travelling from Tulbagh to Gouda. For road users travelling into Tulbagh (north of the R46), the impact is considered to be somewhat less as the line is visible for a brief period as one passes under the line. The line will still be noticeable, but the impact will be reduced by following the route through the valley as recommended in the EIR.
|
Chapter 2,
Section 5.2.3,
Chapter 12
|
Tourism impacts tend to follow the same trend as the visual impact. The Tulbagh valley and the Gydo Pass are seen to receive the greater number of visitors to the area and the Central Route will offer the greatest impact of all the route options (the Southern Route would be the preferred route in this case). However, given the mitigation measures set out in the EIR and outlined in brief above, the anticipated impacts on tourism to the areas is reduced to moderate (from potentially high).
(It is important to note that the growth of the tourism industry in the area was still speculative in many respects, and therefore difficult to quantify in terms of impacts. Tourism bodies were consulted and given the opportunity to participate in the study, and their input was used to make the final assessment. Where these bodies chose not to participate, it was assumed the potential impacts were not perceived to be significant. In this case, the planning of this new line should then inform urban and tourism planners in the review and updating respective development plans.)
|
Chapter 2,
Section 5.2.3,
App 1 - Impact Tables -p7,
Chapter 10
|
Fire fighting and safety. This was not a significant issue along much of the study length of the line, but was raised by the local community as a particular concern in the Tulbagh and Wolseley areas due to serious fires in recent past. The existing 400kV lines past Wolseley have proved to be an obstacle to effective and safe fire fighting. Fire fighters cannot work under the live lines during fires and water bombing from the air is also done at high risk. That the existing 400kV lines are immediately adjacent adds to the problem. The areas around Wolseley and north of Tulbagh are the most problematic for forest fires. In this instance, the Central Route is the preferred option.
|
Chapter 2,
Section 5.2.3,
App 1 - Impact Tables -p10
Chapter 10
|
The above issue leads to the consideration of one of the main technical issues. Due to load capacity and stability requirements it proves to be very difficult to switch off one of the 400kV lines. During forest fires it may be required to switch off both as they are next to each other. For this reason it is necessary to seek a separate route for the new line. On the basis of the environmental considerations outlined above, the Central Route is the preferred option.
|
Chapter 2,
Section 5.2.3,
App 1 - Impact Tables -p2
|
Aspect
|
Level of significance after mitigation on the Central Route
|
Avifauna
|
Low
|
Ecology - fauna & flora
|
Low
|
Cultural heritage
|
Moderate to low
|
Social & socio-economic (incl. tourism)
|
Moderate to low
|
Soils
|
Moderate
|
Visual
|
Moderate
|
Technical (incl. Fire fighting)
|
Low
|